Quarterly Activities and Cashflow Report
Released
Released
Announcement PDF
Visit Investor Hub for a video update
June 2026 Quarterly Activities Report
HIGHLIGHTS
Peru – Cangallo Copper-Gold Project
❑ Stage 3 Reverse Circulation (RC) drilling was successfully completed, defining a
continuous mineralised corridor exceeding 1,500m in length with broad intercepts of
copper-gold mineralisation confirming the large-scale nature of the porphyry system.
❑ Significant broad intercepts reported during the Quarter include:
• 269m @ 0.29% Cu and 0.05g/t Au from 160m (CANRC045) (EOH)
• 214m @ 0.28% Cu and 0.11g/t Au from 124m (CANRC044)
• 184m @ 0.25% Cu and 0.05g/t Au from 208m (CANRC046)
• 92m @ 0.32% Cu and 0.03g/t Au from 102m (CANRC048)
• 176m @ 0.38% Cu and 0.07g/t Au from 40m (CANRC052)
• 342m @ 0.27% Cu and 0.05g/t Au from 30m (CANRC053)
• 236m @ 0.30% Cu and 0.08g/t Au from 2m (CANRC054)
❑ Higher copper (+gold) grades were prevalent in the south, with multiple +0.5% Cu
intervals highlighting strong potential for a porphyry centre in this area. Significant high-
grade results include:
• 12m @ 1.09% Cu and 0.01g/t Au from 112m (CANRC048)
• 12m @ 0.77% Cu and 0.08g/t Au from 102m (CANRC047)
• 6m @ 0.87% Cu and 0.17g/t Au from 4m (CANRC045)
• 10m @ 0.61% Cu and 0.09g/t Au from 276m (CANRC045)
• 6m @ 0.67% Cu and 0.09g/t Au from 378m (CANRC045)
• 14m @ 0.56% Cu and 0.15g/t Au from 332m (CANRC046)
• 12m @ 0.50% Cu and 0.43g/t Au from 138m (CANRC044)
❑ Stage 3 diamond drilling (~6 holes for +5,000m) commenced late in the Quarter, with the
first drill-hole (CANDD003) confirming the substantial vertical extent of the mineralised
porphyry system in the southern area – assays are pending.
❑ Diamond drilling is expected to continue for several months with assay results expected ~4
weeks after completion of each drill-hole.
❑ Permitting of the Stage 4 drill pads has progressed with final approval expected within the
next Quarter to enable drilling of the southern and eastern extensions to commence.
❑ The potential for this exciting new copper discovery continues to grow, with each new
drilling program increasing the extent of the mineralisation as well as the potential for
higher-grade hypogene mineralisation beneath the depth of RC drilling.
Peru – Copper-Gold Projects
❑ Reconnaissance RC drilling (12 holes for 3,733m) at Playa Kali highlighted the potential
for widespread iron-oxide copper-gold (IOCG) systems under cover.
❑ Significant assay results included 12m @ 0.2% Cu and 0.05g/t Au (BOH) in PKRC007;
10m @ 0.37% Cu in PKRC009; 28m @ 218ppm Mo (including 4m @ 617ppm Mo) in
PKRC004; and anomalous Cu (350ppm to 0.21% Cu) in PKRC001.
Australia – Copper, Zinc, Nickel, Gold, Iron
❑ At Coober Pedy (SA), diamond drilling (~3,000m) is scheduled to commence in early
August to test geophysical targets for iron-oxide copper-gold (IOCG) mineralisation.
❑ At Balladonia (WA), permitting for a planned RC drill program (~8,000m) has progressed
with drilling now anticipated to commence in Q4 CY2026.
❑ At Mt Davis (WA), heritage surveys will commence in late July to allow ground
geophysical surveys to be completed in Q3 CY2026 to identify further targets for drilling.
Corporate
❑ Quarter-end cash position of ~$6.4 million, which includes funds provided by South32 to
complete drilling programs at Balladonia and Coober Pedy.
Figure 1: Project Locations – Australia and Peru.
OVERVIEW
During the June Quarter, AusQuest continued
its drilling campaign at the exciting Cangallo
porphyry copper-gold discovery in Peru and
undertook maiden drilling programs at the
nearby Playa Kali and Lantana Prospects in
order to advance the Company’s evaluation of
the Cangallo District’s potential to host
significant copper-gold resources.
In Australia, drilling at the Balladonia
Project is now scheduled for Q4 CY2026
despite the Company’s efforts to fast-track the
approvals process, whilst at Coober Pedy
diamond drilling is now planned to test the
key targets after the initial drilling campaign
was suspended during the quarter due to poor
RC drilling conditions. Elsewhere, heritage
surveys for geophysical work programs were
planned and evaluation of the Company’s
Morrisey Magnetite Project continued.
All current projects in Australia are funded
under the Strategic Alliance Agreement
(SAA) with a wholly-owned subsidiary of
South32 Limited (South32).
PERU COPPER-GOLD PROJECTS
AusQuest has assembled a strong portfolio of
copper-gold prospects along the southern
coastal belt of Peru in South America, with
numerous targets identified for drilling as
possible porphyry copper and/or replacement
style (manto) IOCG targets with size potential
being of significance to AusQuest (Figure 2).
Peru is one of the world’s most prominent
destinations for copper exploration and is
considered a prime location for world-class
exploration opportunities.
Figure 2: Project Locations – Southern Peru.
Cangallo Copper-Gold Project (100%
AQD)
The Cangallo Porphyry Copper-Gold
Discovery is located approximately 30km
west of the town of Chala in southern Peru,
along the same E-W structures that appear to
control the emplacement of potential
porphyry copper systems in the region. The
tenements, which cover an area of ~ 60km²,
are very well located, being ~8km from the
coast, close to infrastructure, and at an
elevation between 500 and 1,200 metres.
Geological mapping and rock-chip sampling
originally identified a partially exposed
copper (+/- gold) porphyry system within a
large-scale (minimum 3km x 2km) caldera-
like structure containing extensive colluvial
and younger sediments.
During the Quarter, the Stage 3 RC drilling
program was completed for a total of 54 RC
drill-holes and ~21,600m of drilling. All assay
results have been received and continue to
demonstrate the large scale and continuity of
the copper (gold) mineralisation, as well as
the emerging potential for higher-grade
mineralisation both in the south and north of
the prospect (JORC tables for the RC drilling
program have been included in ASX releases
dated 28/08/2025, 04/03/2026, and
05/05/2026).
All significant intersections returned from the
Stage 3 RC and diamond drilling programs
are provided in Appendix 1 and Appendix 2
respectively, with drill-hole locations shown
in Figure 3
Figure 3: Cangallo Prospect showing the location of the Stage 3 RC drill-holes with copper profiles plus
completed and planned diamond drill sites (surface rock-chip assays first reported in ASX releases – 30
March and 09 November 2023).
Assay results reported during the Quarter
highlight further broad copper intersections
(+200m, +0.25% Cu) within stockwork
veined volcanic host rocks in the south of the
prospect, plus higher copper grades (>0.5%
Cu) within mineralised intrusive dykes which
appear to be more prevalent in this area
(Figure 4).
Figure 4: Cangallo South Prospect showing increased grade and thickness towards the south-east and the
location of diamond drill-hole CANDD003 (assays first released 4th March and 29th May 2026).
Multiple RC drill holes throughout the
prospect area ended in mineralisation,
suggesting that the boundaries of the
mineralised porphyry system are still wide
open – and will be further tested as part of the
Stage 4 drilling program.
Multiple drill intercepts of +0.5% Cu over
greater than 10 metres in thickness have been
reported from the Stage 3 drilling program,
providing a high degree of optimism that
higher grade zones will be defined within the
porphyry system as drilling progresses (see
Table 1 below).
These intersections occur within the broader
mineralised envelope (>0.1% Cu),
demonstrating the capability of the system to
produce higher-grade copper either through
supergene enrichment processes or as
hypogene mineralisation within dykes and
stockwork veins occurring with the greater
porphyry system.
Most of the higher-grade intercepts occur
within the oxide zone and are associated with
copper oxides (malachite, chrysocolla,
atacamite) and/or secondary copper sulphides
(chalcocite, bornite and rare covellite) that
occur within the top ~300 metres of section
and may be recoverable using heap leaching
techniques.
Table 1: Significant +0.5% Cu intersections greater than 10 metres down-hole thickness
Hole ID
From
(m) To (m) Int (m) Cu% Hole ID
From
(m) To (m) Int (m) Cu%
CANRC001 252 264 12 0.53 CANRC044 222 232 10 0.51
CANRC001 324 334 10 0.51 CANRC045 276 286 10 0.61
CANRC002 224 234 10 0.51 CANRC046 332 346 14 0.56
CANRC002 362 372 10 0.57 CANRC047 102 114 12 0.77
CANRC003 146 160 14 0.56 CANRC048 112 124 12 1.09
CANRC003 164 182 18 0.55 CANDD052 46 56 10 0.50
CANRC003 260 270 10 0.5 CANDD052 112 128 16 0.50
CANRC007 352 362 10 0.51 CANDD052 138 156 18 0.53
CANRC008 36 46 10 0.72 CANDD052 168 178 10 0.50
CANRC008 50 64 14 0.52 CANDD052 192 210 18 0.55
CANRC012 36 104 68 0.52 CANDD053 214 224 10 0.50
CANRC014 96 120 24 0.50 CANDD053 244 254 10 0.60
CANRC014 134 152 18 0.62 CANDD054 174 184 10 0.50
CANRC014 186 200 14 0.52 CANDD002 120 130 10 0.50
CANRC032 10 20 10 0.65 CANDD002 354 374 20 0.56
CANRC032 156 186 30 0.60 CANDD002 416 426 10 0.51
CANRC034 388 398 10 0.51 CANDD002 470 480 10 0.53
CANRC044 138 150 12 0.5 CANDD002 546 556 10 0.50
Recent intersections of 12 metres @ 1.09%
Cu (CANRC048) and 12 metres @ 0.77% Cu
(CANRC047) within porphyritic quartz
diorite dykes highlight the potential of the
system to also host higher copper grades
within the source (parent) porphyry stock (the
true thickness and orientation of these dykes
is not known at this stage given the broad-
spacing and nature of the RC drilling
completed to date).
Gold values associated with the copper
intersections appear to be increasing to the
south, particularly in drill-hole CANRC044,
which contains several intercepts (>10m)
reporting average gold grades ranging from
0.15g/t Au to 0.43g/t Au (see Appendix 1).
This gold trend is supported by earlier surface
sampling results which suggest increased
potential for gold in the southern area.
Diamond drilling designed to test for deeper
hypogene copper mineralisation below the
current depth limit (~350 metres) of RC
drilling commenced late in the Quarter, with
the first drill-hole (CANDD003), located
within the southern mineralised corridor,
completed at a depth of ~880m.
Importantly, this program will provide critical
geological information that will help to vector
towards higher-grade copper mineralisation
that extends to depth.
Logging of drill-core from CANDD003
shows copper occurring in stockwork veins
from near surface to approximately 550m
depth, within a package of andesite and dacite
volcanics intruded by quartz diorite and
tonalite dykes. Below 550m depth, the
mineralised vein density appears to decrease,
but remains present at the end of hole,
confirming the large vertical extent of the
stockwork vein complex – assay results for
this hole are pending.
Copper oxides were logged to depths
exceeding 250m with chalcocite observed
from approximately 250m to 280m,
suggesting the presence of a supergene zone
that may be developed above a potential
sulphide system. Below ~280 metres, primary
copper sulphides (chalcopyrite ± pyrite and
rare bornite +/-molybdenite) occur in
stockwork veins and disseminations within
the volcanics.
The primary copper mineralisation is
associated with extensive quartz-
sericite/muscovite-chlorite veining with
several hydrothermal breccia zones also
evident in the core, suggesting multiple
intrusive and mineralising events which is
typical of a large mineralised porphyry
system (Figures 5 and 6 – Refer ASX release
22 July 2026).
Figure 5: Core photos from CANDD003 showing chalcopyrite-filled veins at 308m (LHS) – disseminated
chalcopyrite in porphyritic andesite host rock at 383m (centre); Muscovite-chlorite veins with K feldspar
selvages and chalcopyrite either disseminated or forming centrelines in the veins at 504m (RHS).
Figure 6: Core photos from CANDD003 showing breccias within the oxide zone with disseminated chalcocite
(black) at 134m (LHS) – Breccia within the sulphide zone showing potassic alteration, chlorite muscovite
veins with disseminated chalcopyrite at 382m (RHS).
“Visual estimates of mineral abundance should never be considered a proxy or substitute for laboratory
analyses where concentrations or grades are the factor of principal economic interest. Visual estimates also
potentially provide no information regarding impurities or deleterious physical properties relevant to
valuations.”
Further diamond drilling in the southern area
will be undertaken once assay results have
been received and assessed. Diamond drilling
has now commenced in the north of the
prospect where multiple drill-holes finished in
mineralisation and hypogene copper sulphides
are known to occur to depths of at least 700m.
The diamond drilling program is expected to
continue for several months with assays
available approximately four weeks after the
completion of each drill-hole.
Permitting for the Stage 4 drilling program
(an additional 20 drill pads) has progressed
with MINEM (Mines Department) approval
expected in Q3 CY2026 and final approval
for surface access shortly thereafter. This will
allow the southern and eastern extensions of
the porphyry system to be further tested by
drilling.
Playa Kali IOCG Project (100% AQD)
The Playa Kali Project is located ~10km east
of the coastal town of Chala and ~120km
south-east of the Mina Justa copper deposit
(~475Mt @ 0.68% Cu). It consists of six
mineral claims covering an area of ~33km²
and was acquired after manto-style
mineralisation (including massive magnetite
layers with up to 1m thick bands of sulphides
containing anomalous copper and gold values
up to 1.9% Cu and 1g/t Au), was located
within a sequence of sediments similar to
those found in the vicinity of the Marcona and
Mina Justa deposits to the north. Geological
mapping, rock-chip sampling and ground
magnetic surveys have been completed over
the tenements, defining target areas for
drilling, targeting manto-style copper-gold
deposits.
During the Quarter, reconnaissance RC
drilling (12 holes for a total of 3,733m) was
completed to provide a first-pass test of a
range of geophysical, geological (structural)
and geochemical features at the eastern end of
the Project that were interpreted to reflect a
new manto (iron oxide) target area for copper
and gold mineralisation, similar to that found
at the Mina Justa deposit ~100km to the north
(Figure 7).
Drilling intersected a mixed package of
volcanics (andesites and dacites) and
sediments (sandstones and siltstones)
containing variable amounts of disseminated
magnetite (+ pyrite), with highly anomalous
copper values (>1,000ppm Cu) intersected in
many of the drill-holes, highlighting the
potential for copper (+/- gold) in the
surrounding areas.
Figure 7: Playa Kali Project showing drill-hole locations relative to mapped geology and the magnetic
complexes plus anomalous copper values from the RC drilling program – Refer ASX release 8 July 2026.
Significant assay results from this
reconnaissance program included: 12m @
0.2% Cu and 0.05g/t Au (BOH) in PKRC007;
10m @ 0.37% Cu in PKRC009; 28m @
218ppm Mo (including 4m @ 617ppm Mo) in
PKRC004; and anomalous Cu (350ppm to
0.21% Cu) in PKRC001.
Drill-holes PKRC001 and PKRC004 are
located close to regional east-west structures
which have strongly developed alteration
(jarosite, goethite and hematite), and are
thought to be one of the controlling features
for IOCG copper mineralisation in the area.
A review of all the multi-element
geochemical data from both the drilling and
surface sampling programs, as well as
magnetic modelling is currently in progress to
define and prioritise target areas for future
drill testing and/or geophysical surveys.
Lantana Porphyry Copper Prospect (100%
AQD)
The Lantana Prospect is located ~30km east
of the Company’s Cangallo Prospect in an
area where surface indicators of porphyry
copper mineralisation have been identified.
The prospect occurs at the eastern end of the
Cerro de Fierro/Pirata Project, and occurs
within a major E-W structural corridor that is
considered to be a priority target zone for
porphyry copper deposits within the coastal
belt of southern Peru.
The reconnaissance RC drilling program (nine
holes for a total of 2,794m) was completed
around the end of the Quarter with samples
subsequently sent to the laboratory for assay.
Results of the analyses will be reported to
market once they have all been received and
assessed.
The drill program was designed to test for
porphyry copper mineralisation in areas with
widespread occurrences of highly anomalous
copper, molybdenum and bismuth values that
were obtained from rock-chip sampling.
Parcoy IOCG Project (100% AQD)
The Parcoy Project is located near the
southern end of a recognised IOCG
metallogenic belt in southern Peru. It lies
within ~100km of the Mina Justa deposit
(~475Mt @ 0.68% Cu), and ~50km north-
west of the Company’s Cerro de Fierro
Project. Geological mapping and rock-chip
sampling has identified significant
concentrations of copper (+/- gold) at
surface, reflecting potential manto-style
mineralisation within the volcanic
stratigraphy.
No work was completed during the Quarter
while efforts were focused on the nearby
Cangallo Project. The Company believes that
there are copper targets at Parcoy that were
not tested by the initial wide-spaced drilling
programs and is considering its options for the
project.
AUSTRALIA – BASE METAL
PROJECTS (Copper, Zinc, Nickel & REE)
Balladonia Zinc-Copper (+/- Nickel and
REE) Project (100% AQD, subject to SAA)
The Balladonia Project is located ~50km
south of the Nova–Bollinger nickel-copper
deposit in Western Australia. It consists of 11
Exploration Licences (six granted and five
applications) covering an area of ~1,350km²
and is located within a structurally complex
region of the Fraser Range Terrane.
Exploration at Balladonia has indicated
potential for multiple mineralisation styles
with many priority targets identified. This
includes the potential for nickel and copper
mineralisation similar to the Nova deposit, as
well as iron-oxide copper-gold (IOCG) and
Broken Hill Type (BHT) deposits similar to
those found in the Eastern Succession (NW
Queensland) and in NSW. More recently, the
potential for rare earth elements (REE)
associated with carbonatite intrusions has
also been recognised. Many of the tenements
lie within the Dundas Reserve. Exploration
work at Balladonia is funded under the SAA.
During the Quarter, a Flora and Fauna survey
was completed over all the proposed drill
targets as part of the approvals process to
allow the planned drilling program to
commence. No obvious impediments to the
program were reported.
Figure 8: Balladonia Project showing target locations and planned drill-holes in relation to Magnetic Image.
The Company has been advised that its
Reserve Activity Management Plan (RAMP)
to approve the planned exploration drilling
inside the Dundas Nature Reserve (DNR) is
progressing through the Government system.
The Company anticipates that approval in full
or otherwise could be provided within Q3
CY2026, allowing drilling to start in Q4
CY2026.
The planned RC drilling program (~65 holes
for a total of ~8,000m) will test a range of
targets for lead-zinc and copper-gold
mineralisation under the SAA (Figure 8).
The drilling program will initially focus on
targets within the DNR with priority given to
structural sites within and adjacent to the
main Tea Tree sequence as well as distinct
magnetic/gravity targets offset from the Tea
Tree Trend.
Coober Pedy Copper-Gold Project (100%
AQD, subject to SAA)
The Coober Pedy Project is located ~15km
SW of the town of Coober Pedy, South
Australia, on the north-eastern margin of the
Gawler Craton, approximately 100km NW of
the Prominent Hill Copper-Gold Deposit. The
Project, which consists of one Exploration
Licence covering an area of ~170km², was
acquired to explore for iron-oxide copper-
gold (IOCG) deposits. Regional magnetic and
gravity data, together with analytical results
from historical drilling (five holes),
highlighted the prospectivity of the area.
Exploration work at Coober Pedy is funded
under the SAA.
During the Quarter, the Company’s maiden
RC drilling program (~13 holes for ~4,500m)
commenced, to test a combination of
geophysical targets for IOCG mineralisation
located close to the interpreted position of the
Elizabeth Creek Fault Zone.
Figure 9: Coober Pedy Project showing planned and completed RC drilling in relation to magnetic image and
residual gravity contours and IP anomalies (refer ASX release 17 July 2025).
Three (3) holes successfully reached the
targeted basement rocks before operations had
to be suspended due to the failure to penetrate
an extensive, unconsolidated dry quartz sand
unit (~30m thick) located immediately above
basement (Figure 9)
Two of the successful drill-holes were located
at the Bulldog prospect, ~400m from a
historical Vale drill-hole (GAWRC001), and
intersected mafic to intermediate gneissic
rocks with variable chlorite alteration and up
to 5% sulphides (mainly pyrite).
Assay results for these drill-holes are pending.
The Company plans to complete the original
drilling program using mud rotary drilling
techniques to penetrate the cover sequence
and diamond tails to test the targeted
basement rocks. Diamond drilling (~10 holes
for ~3,500m), is expected to re-commence in
early August to test the priority target areas
defined by magnetic, gravity and Induced
Polarisation surveys.
Morrisey Magnetite, Nickel-Copper-PGE
Project (100% AQD, subject to SAA)
The Morrisey Project is located ~500km north
of Perth in Western Australia within the
Midwest mining district. The project occurs
within the high-grade metamorphic Narryer
Terrane, which forms the north-western
margin of the Yilgarn Craton. It consists of
three granted Exploration Licences and two
applications covering an area of ~1,300km²
and is located ~120km north of the town of
Mullewa, where there is rail access to the
Port of Geraldton 80km away.
Reconnaissance drilling to test magnetic
targets intersected coarse grained magnetite
which could be upgraded via magnetic
separation methods to a premium iron
product (>70% Fe) potentially suitable for
green iron smelting. Exploration work at
Morrisey is funded under the SAA.
Figure 10: Morrisey Magnetite Project showing the location of the new Dann Bore prospect in relation to the
location of the Waterfall Prospect and magnetics.
During the Quarter, the Company completed a
review of existing geophysical and drilling
data at Morrisey to help provide guidance for
the next phase of work given the possibility of
cumulative magnetite occurrences in the area.
This resulted in a new Exploration Licence
application being submitted to secure
additional magnetic targets close to the
Waterfall Prospect with the potential to add
significantly to the Project’s magnetite
inventory (Figure 10).
Coarse grained magnetite at the Waterfall
Prospect, which can be upgraded to +70% Fe
using a coarse grind size (75um), occurs in a
high-grade metamorphic iron formation (IF)
which the Company believes is the preferred
host rock for the better magnetite deposits in
the area.
Further evaluation of the Morrisey Magnetite
Project is being planned under the SAA.
Mt Davis Lead-Zinc-Copper Project (100%
AQD, subject to SAA)
The Mt Davis Project is located ~180km NNE
of Wiluna, Western Australia, along the
northern margin of the Earaheedy Basin. It
consists of three Exploration Licences (two
granted and one application) covering an
area of ~1,275km². The project was acquired
following the discovery of extensive zinc and
copper mineralisation by Rumble Resources
at its Chinook Prospect, located on the
southern side of the Basin, where
mineralisation is stratigraphically controlled
and located below the Frere Iron Formation.
The Mt Davis tenements are believed to
contain similar stratigraphy but in an area of
greater structural complexity which has been
reported as an important factor in the
localisation of higher grades at Chinook.
Exploration work at Mt Davis is funded under
the SAA.
During the Quarter, planning for ground
geophysical surveys continued, with Heritage
Clearance surveys to be completed in late
July.
Ground electromagnetic (EM) surveys have
been designed to test target areas where a
combination of VTEM and magnetic data
highlights the possibility for sediment-hosted
base metal deposits to be found,
stratigraphically below the Frere Iron
Formation and close to major structures along
the northern margin of the Earaheedy Basin.
Assay results from earlier RC drilling
provided sufficient encouragement to
undertake further exploration in the region to
identify additional targets for drilling (ASX
release 23rd
December 2025).
Hamilton Copper-Gold Project (100%
AQD)
The Hamilton Project is located in north-west
Queensland, ~120km south of the world-class
Cannington mine and ~70km south of the
Osborne copper mine. It consists of two
Exploration Licences covering an area of
~260km². Exploration is targeting iron oxide,
copper, gold (IOCG) and Broken Hill Type
(BHT) mineralisation beneath the extensive
cover in the region. Limited drilling
completed to date to test magnetic and gravity
targets provided evidence for “near-miss”
situations which are the focus of the
Company’s ongoing exploration.
Further work at this prospect is under
consideration in view of other higher
Company priorities.
New Opportunities (Australia):
New opportunities within Australia continue
to be assessed by the Company’s consultants.
CORPORATE
At the end of the June Quarter, the Company
had approximately $6.4 million in cash after
investing ~$4.5 million in exploration. These
funds include contributions from South32 to
cover work programs in Australia that have
been agreed under the SAA.
The Company’s Cashflow Report (Appendix
5B) for the Quarter ended 30 June 2026 is
appended to this report. Payments to related
parties as shown in Section 6 of this report
include director salary and superannuation
payments of $111,000.
KEY ACTIVITIES – SEPTEMBER 2026
QUARTER
• Peru (Cu-Au) – Complete Stage 3
diamond drilling (+5,000m) at
Cangallo.
• Peru (Cu-Au) – Facilitate Stage 4 drill
permit approvals at Cangallo (20 drill
pads; +50,000m RC/diamond drilling).
• Peru (Cu-Au) – Continue geological /
resource assessment at Cangallo.
• Peru (Cu-Au) – Advance metallurgical
understanding at Cangallo.
• Peru (Cu-Au) – Assess RC drill results
at Playa Kali and Lantana.
• Balladonia (Cu-Zn-Au) – Complete
access preparation for RC drilling
(subject to Government approvals)
and commence drill program.
• Morrisey (Magnetite) – Finalise
ongoing evaluation program under the
SAA.
• Coober Pedy (Cu-Au) – commence
diamond drilling program to test
IOCG targets.
• Mt Davis (Cu-Pb-Zn) – Complete
Heritage clearance and ground EM
surveys.
Authorised for release on behalf of the Company by:
Graeme Drew
Managing Director
COMPETENT PERSON’S STATEMENT
The details contained in this report that pertain to exploration results are based upon information compiled by Mr Graeme Drew, a
full-time employee of AusQuest Limited. Mr Drew is a Fellow of the Australasian Institute of Mining and Metallurgy (AUSIMM)
and has sufficient experience in the activity which he is undertaking to qualify as a Competent Person as defined in the December
2012 edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves” (JORC Code).
Mr Drew consents to the inclusion in the report of the matters based upon his information in the form and context in which it
appears.
NO NEW INFORMATION
To the extent that this announcement contains references to prior exploration results which have been cross referenced to previous
market announcements made by the Company, unless explicitly stated, the Company confirms that it is not aware of any new
information or data that materially affects the information included in the relevant market announcements.
FORWARD LOOKING STATEMENT
This report contains forward looking statements concerning the projects owned by AusQuest Limited. Statements concerning
mining reserves and resources may also be deemed to be forward looking statements in that they involve estimates based on
specific assumptions. Forward-looking statements are not statements of historical fact and actual events and results may differ
materially from those described in the forward looking statements as a result of a variety of risks, uncertainties and other factors.
Forward looking statements are based on management’s beliefs, opinions and estimates as of the dates the forward looking
statements are made and no obligation is assumed to update forward looking statements if these beliefs, opinions and estimates
should change or to reflect other future developments.
Announcements to ASX for the Cangallo Project
29/05/2026 Cangallo diamond drilling to commence
05/05/2026 Cangallo Porphyry Copper Continues Growing
25/03/2026 Major new drilling program commences at the Cangallo Copper-Gold Discovery, Peru
04/03/2026 Highly encouraging drill results continue to grow the Porphyry Cangallo Copper-Gold Project
11/02/2026 Cangallo delivers significant Cu extensions extending the porphyry discovery to over 1500m
06/01/2026 Diamond and RC drilling substantially expands scale of copper mineralization at Cangallo
02/12/2025 Stage 3 Drilling commences at the Cangallo Copper-Gold Discovery in Peru
13/11/2025 RC Drilling set to commence at Cangallo
12/11/2025 Diamond Drilling more than doubles depth extent of copper mineralisation at Cangallo
30/09/2025 Diamond Drilling Commences at Cangallo
28/08/2025 Cangallo Porphyry Copper Discovery continues to grow
21/07/2025 Cangallo Drilling Progress Report
12/06/2025 Drilling Commences at Cangallo
24/04/2025 Drilling set to commence at Cangallo
05/03/2025 Drilling to extend Cangallo Cu-Au discovery
06/02/2025 Cangallo Discovery Confirmed
23/01/2025 Significant Porphyry Copper Discovery a
Share your feedback