INCREASING COPPER GRADES AND WIDTHS CONTINUES TO
GROW THE SCALE OF CANGALLO
Highlights
• Wide spaced Reverse Circulation (RC) drilling continues to define a continuous
mineralised corridor exceeding 1500m in length with broad intercepts of copper-gold
mineralisation confirming the large-scale nature of the porphyry system.
• Significant intersections from the first 9 of 13 drill-holes include:
o 269m @ 0.29% Cu and 0.05 g/t Au from 160m (CANRC045) (EOH) including:
38m @ 0.34% Cu and 0.03 g/t Au from 178m
32m @ 0.44% Cu and 0.07 g/t Au from 274m
46m @ 0.38% Cu and 0.06 g/t Au from 346m
o 214m @ 0.28% Cu and 0.11 g/t Au from 124m (CANRC044) including:
30m @ 0.42% Cu and 0.18 g/t Au from 220m
26m @ 0.37% Cu and 0.06 g/t Au from 260m
o 184m @ 0.25% Cu and 0.05 g/t Au from 208m (CANRC046) including:
30m @ 0.44% Cu and 0.10 g/t Au from 328m
o 92m @ 0.32% Cu and 0.03 g/t Au from 102m (CANRC048)
• Higher copper and gold grades within mineralised dykes and stockwork veins are
prevalent in the south, with multiple +0.5% Cu intervals highlighting strong potential for at
least one porphyry centre to be located in this area. Significant results include:
o 12m @ 1.09% Cu and 0.01 g/t Au from 112m (CANRC048)
o 12m @ 0.77% Cu and 0.08 g/t Au from 102m (CANRC047)
o 6m @ 0.87% Cu and 0.17 g/t Au from 4m (CANRC045)
o 10m @ 0.61% Cu and 0.09 g/t Au from 276m (CANRC045)
o 6m @ 0.67% Cu and 0.09 g/t Au from 378m (CANRC045)
o 14m @ 0.56% Cu and 0.15 g/t Au from 332m (CANRC046)
o 12m @ 0.50% Cu and 0.43 g/t Au from 138m (CANRC044)
• The potential of the Cangallo copper discovery continues to grow with extensive near-
surface copper oxide mineralisation and strong indications of higher grade hypogene
mineralisation in a strategic location close to the coast and key infrastructure.
• Assay results from 4 of the 13 RC drill-holes are outstanding with +5,000m diamond drill
program planned for late May to target higher‑grade copper sulphide extensions at depth.
• Permitting of the Stage 4 drill pads has been prioritised to enable further drilling in the
highly prospective southern portion of the prospect as soon as possible.
2
AusQuest Limited (“AusQuest” or the “Company”) (ASX: AQD) is pleased to report the
successful completion of the Stage 3 RC drilling program at its 100%-owned Cangallo
Porphyry Copper-Gold Project in Peru, with results continuing to demonstrate both the scale
and emerging grade potential. A full assessment of the newly received geochemical data is in
progress.
The current round of the Stage 3 RC drilling program was designed to confirm the continuity
of the mineralisation intersected in Stages 1 and 2 and to further evaluate the scale potential
of the Cangallo porphyry copper-gold system. Results to date continue to support the
interpretation that Cangallo is a very large and laterally continuous porphyry system,
extending over more than 1,500 metres in length (see Figure 1 for plan-view and Figure 2 for
long section).
Figure 1: Cangallo Prospect showing location of Stage 3 RC drill-holes with copper profiles and potential
extensions inferred by drilling and surface copper and gold anomalism (Surface rock-chip assays first
reported in ASX releases - 30 March and 09 November 2023).
3
Figure 2: Long Section A-A’ showing the open-ended extent of copper mineralisation defined to date by
the RC drilling program.
To date, assay results from 9 of the 13 drill-holes (from the southern sections) have been
received, highlighting both broad copper intersections within the stockwork veined volcanic
host rocks, and higher copper grades (>0.5% Cu) within mineralised intrusive dykes which
appear to be more prevalent in the south.
In particular, intercepts of 12 metres grading 1.09% Cu (CANRC048) and 12 metres grading
0.77% Cu (CANRC047) occur within porphyritic quartz diorite dykes, highlighting the
potential of the system to produce higher copper grades within the source (parent) porphyry
stock. The true thickness and orientation of these dykes is not known at this stage given the
broad-spacing and nature of the drilling (RC) completed to date.
Further +0.5% Cu intervals greater than 10 metres in thickness have been reported within the
current assay results. These include:
Hole ID From (m) To (m) Interval (m) Cu %
CANRC044 138 150 12 0.50
CANRC044 222 232 10 0.51
CANRC045 276 286 10 0.61
CANRC046 332 346 14 0.56
CANRC047 102 114 12 0.77
CANRC048 112 124 12 1.09
These intersections occur within the broader mineralised envelope (>0.1% Cu), demonstrating
the capability of the system to produce higher-grade copper either through supergene
enrichment processes or as hypogene mineralisation within dykes and stockwork veins
occurring with the porphyry system.
4
Gold values associated with the copper intersections also appear to be increasing to the south
particularly in drill-hole CANRC044, the south-easternmost drill-hole, which contains several
intercepts (>10m) reporting average gold grades ranging from 0.15g/t Au to 0.43g/t Au (see
Table 1). This gold trend is supported by earlier surface sampling results which suggest
increased potential for gold in the southern area.
Most of the higher-grade intercepts occur within the oxide zone and are associated with copper
oxides (malachite, chrysocolla, atacamite) and/or secondary copper sulphides (chalcocite,
bornite and rare covellite) that occur within the top ~300 metres of section and may be
recoverable using heap leaching techniques.
Next Steps
A full assessment of the multi-element geochemistry and geology from the RC drilling program is
in progress to identify areas within this large-scale system where higher-grade hypogene copper
mineralisation is more likely to occur. Vectors from this work will be used to guide deeper diamond
drilling to test targets identified by this process.
Diamond drilling (+5,000m) is scheduled to commence in late May to help locate higher‑grade
depth extensions of the copper sulphide mineralisation. Priority sites for the diamond drill-holes
will be finalised once all RC assay data has been received and assessed.
Permitting for the Stage 4 drill pads has been prioritised to facilitate further drilling in the south of
the prospect as soon as possible, following the encouraging drilling results reported from the
southern drill-section. It is anticipated that the permits should be available in Q3 CY2026 to allow
Stage 4 drilling to commence shortly thereafter.
Commenting on the latest results, AusQuest’s Managing Director, Graeme Drew, said:
“These results continue to reinforce Cangallo as a large and growing porphyry copper system,
with mineralisation now defined over more than 1.5 kilometres of strike and remaining open in
multiple directions.
Importantly, we are now seeing higher-grade copper emerging within the system, including
results exceeding 1% Cu – which supports our view that we are vectoring towards a higher-
grade core. The potential for higher copper grades is an exciting development for the project
given the broad spaced nature of our current drilling.
We are encouraged to see that copper continues to occur from surface and is oxidised to
depths of 200 to 250m, making it a viable proposition for an early open-cut operation, with the
shallow copper potentially recoverable by heap leaching – a low-cost processing option.
“Deeper hypogene sulphide mineralisation that is associated with multi-phase vein systems
containing chalcopyrite and bornite, and potential porphyry stock systems, will be targeted by
the upcoming diamond drilling once the RC drilling results have been fully assessed.
“We look forward to receiving assay results for the remaining drill-holes which should add
further to the Cangallo story, and keeping shareholders updated on results as they become
available.”
Peru: Scale and Grade / Early comparisons
Peru is one of the largest copper producers in the world behind Chile, with around 2.8Mt of
copper being mined and processed per annum. The bulk of this production comes from large
porphyry copper projects that are located along the Andean Belt that extends from Chile in the
south to Ecuador in the north.
5
Porphyry deposits are typically large (often over 1 billion tonnes of ore) and usually open-
cuttable with low waste to ore ratios. The shallower parts of these ore bodies are usually oxide
ores that can be processed using heap leach methods, resulting in lower development and
operational costs and positive short-term cash flow.
Copper grades for the oxidised ores are generally lower (except where there is a supergene
enriched zone) than the deeper hypogene ores which require more expensive mining and
processing methods.
There are a number of profitable large-scale porphyry copper operations within the Arequipa
District where Cangallo is located as well as potential developments at Zafranal and Tia Maria,
using head grades between 0.20% and 0.40% Cu. These mines have multi-decade mine-lives
and are long-lived assets.
The economic viability of the Peruvian resources is often affected by a range of issues
including location, altitude, proximity to infrastructure and water, as well as land usage conflicts
with local communities. In this regard Cangallo is well placed.
The Cangallo Project is particularly well located with respect to the above, being close to
significant infrastructure, 25km east of the town of Chala and at low altitudes within 10km of
the coast. Community consultation has formed part of the Company’s exploration process, with
no critical issues identified to date.
Peru is a stable country and the government is supportive of new mine developments as they
add significantly to the Peruvian economy and the communities where they are located.
Graeme Drew
Managing Director Visit Investor Hub for further updates
COMPETENT PERSON’S STATEMENT
The details contained in this report that pertain to exploration results are based upon information compiled by Mr
Graeme Drew, a full-time employee of AusQuest Limited. Mr Drew is a Fellow of the Australasian Institute of Mining
and Metallurgy (AUSIMM) and has sufficient experience in the activity which he is undertaking to qualify as a
Competent Person as defined in the December 2012 edition of the “Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves” (JORC Code). Mr Drew consents to the inclusion in the report of
the matters based upon his information in the form and context in which it appears.
NO NEW INFORMATION
To the extent that this announcement contains references to prior exploration results which have been cross
referenced to previous market announcements made by the Company, unless explicitly stated, the Company
confirms that it is not aware of any new information or data that materially affects the information included in the
relevant market announcements.
FORWARD-LOOKING STATEMENT
This report contains forward looking statements concerning the projects owned by AusQuest Limited. Statements
concerning mining reserves and resources may also be deemed to be forward looking statements in that they
involve estimates based on specific assumptions. Forward-looking statements are not statements of historical fact
and actual events and results may differ materially from those described in the forward looking statements as a
result of a variety of risks, uncertainties and other factors. Forward looking statements are based on management’s
beliefs, opinions and estimates as of the dates the forward looking statements are made and no obligation is
assumed to update forward looking statements if these beliefs, opinions and estimates should change or to reflect
other future developments
6
*Announcements to ASX for the Cangallo Project
2023 – 2026 Quarterly Activities and cashflow Reports
25/03/2026 Major new drilling program commences at the Cangallo Copper-Gold Discovery, Peru
04/03/2026 Highly encouraging drill results continue to grow the Porphyry Cangallo Copper-Gold Project
11/02/2026 Cangallo delivers significant Cu extensions extending the porphyry discovery to over 1500m
06/01/2026 Diamond and RC drilling substantially expands scale of copper mineralization at Cangallo
02/12/2025 Stage 3 Drilling commences at the Cangallo Copper-Gold Discovery in Peru
13/11/2025 RC Drilling set to commence at Cangallo
12/11/2025 Diamond Drilling more than doubles depth extent of copper mineralisation at Cangallo
30/09/2025 Diamond Drilling Commences at Cangallo
28/08/2025 Cangallo Porphyry Copper Discovery continues to grow
21/07/2025 Cangallo Drilling Progress Report
12/06/2025 Drilling Commences at Cangallo
24/04/2025 Drilling set to commence at Cangallo
05/03/2025 Drilling to extend Cangallo Cu-Au discovery
06/02/2025 Cangallo Discovery Confirmed
23/01/2025 Significant Porphyry Copper Discovery at Cangallo
17/12/2024 Drilling commences at Cangallo in Peru
Table 1: Significant intersections from Stage 3 - RC drill-holes CANRC042 to 050.
Hole Number From (m) To (m) Interval (m) Cu % Au ppm Mo ppm Ag ppm
CANRC042 34 96 62 0.27 0.09 12 0.09
252 308 56 0.23 0.02 22 0.35
340 392 52 0.17 0.04 14 0.25
CANRC043 48 92 44 0.2 0.07 14 0.06
100 124 24 0.25 0.03 12 0.09
including 110 124 14 0.35 0.20 13 0.10
252 302 50 0.12 0.02 20 0.12
310 354 44 0.12 0.01 17 0.14
CANRC044 16 84 68 0.17 0.06 10 0.07
102 112 10 0.35 0.04 12 0.20
124 338 214 0.28 0.11 28 0.68
including 124 134 10 0.46 0.15 7 0.54
including 138 150 12 0.50 0.43 11 0.55
including 220 250 30 0.42 0.18 28 0.90
including 260 286 26 0.37 0.06 38 0.84
CANRC045 56 92 36 0.12 0.04 15 0.06
102 126 24 0.14 0.01 13 0.03
132 144 12 0.19 0.03 13 0.48
160 429 EOH 269 0.29 0.05 13 0.55
including 178 216 38 0.34 0.03 11 0.33
including 274 306 32 0.44 0.07 16 0.88
including 276 286 10 0.61 0.09 13 1.08
including 328 338 10 0.33 0.07 28 1.07
including 346 392 46 0.38 0.06 14 0.58
CANRC046 56 92 36 0.17 0.03 19 0.10
126 152 26 0.13 0.02 17 0.30
160 178 18 0.27 0.04 18 0.77
208 392 184 0.25 0.05 17 0.46
7
including 328 358 30 0.44 0.10 18 0.64
including 332 346 14 0.56 0.15 20 0.81
CANRC047 68 82 14 0.13 0.06 11 0.05
102 114 12 0.77 0.08 9 0.06
178 226 48 0.27 0.03 25 0.29
including 204 216 12 0.46 0.04 22 0.30
270 398 128 0.21 0.04 17 0.39
including 360 370 10 0.35 0.19 30 0.58
406 444 EOH 38 0.21 0.04 17 0.39
CANRC048 40 94 54 0.20 0.01 12 0.09
102 194 92 0.32 0.03 23 0.46
including 112 124 12 1.10 0.01 7 0.24
CANRC 050 38 72 34 0.25 0.09 7 0.09
including 44 56 12 0.38 0.15 10 0.13
110 202 92 0.21 0.03 9 0.35
including 112 122 10 0.42 0.01 8 0.17
226 452 226 0.21 0.05 12 0.36
including 390 408 18 0.43 0.08 8 0.80
Broad copper intervals determined using a 0.1% Cu cut-off and an internal waste of 6 metres.
Gold, molybdenum and silver values were averaged for same intervals as the copper intersections
Higher grade intervals(including) were determined using 0.3% Cu cut-off and 6 metre waste
intervals and a minimum 10m interval
1
JORC Code, 2012 Edition – Table 1 report, Reverse Circulation Drilling at Cangallo
in Peru
Section 1 Sampling Techniques and Data
(Criteria in this section apply to all succeeding sections.)
Criteria JORC Code explanation Commentary
Sampling
techniques
• Nature and quality of sampling (eg cut channels, random chips, or specific specialised
industry standard measurement tools appropriate to the minerals under investigation,
such as down hole gamma sondes, or handheld XRF instruments, etc). These examples
should not be taken as limiting the broad meaning of sampling.
• Include reference to measures taken to ensure sample representivity and the appropriate
calibration of any measurement tools or systems used.
• Aspects of the determination of mineralisation that are Material to the Public Report.
• In cases where ‘industry standard’ work has been done this would be relatively simple
(eg ‘reverse circulation drilling was used to obtain 1 m samples from which 3 kg was
pulverised to produce a 30 g charge for fire assay’). In other cases more explanation
may be required, such as where there is coarse gold that has inherent sampling
problems. Unusual commodities or mineralisation types (eg submarine nodules) may
warrant disclosure of detailed information.
• Samples are collected using a tube sampler by spearing
into each one metre sample bag and compositing samples
on a two-metre basis.
• Sample depths are determined by the length of the rod-
string and confirmed by counting the number of samples
and bags at the drill platform as per standard industry
practice.
• A ~4kg sample is collected for representivity.
Drilling techniques • Drill type (eg core, reverse circulation, open-hole hammer, rotary air blast, auger,
Bangka, sonic, etc) and details (eg core diameter, triple or standard tube, depth of
diamond tails, face-sampling bit or other type, whether core is oriented and if so, by
what method, etc).
• RC Drilling with a face sampling bit has been used with a
hole diameter of approximately 132mm.
• Down-hole surveys are recorded at 10m intervals using a
down-hole gyroscope probe.
Drill sample
recovery
• Method of recording and assessing core and chip sample recoveries and results
assessed.
• Measures taken to maximise sample recovery and ensure representative nature of the
samples.
• Whether a relationship exists between sample recovery and grade and whether sample
bias may have occurred due to preferential loss/gain of fine/coarse material.
• Experienced RC drillers and an appropriate rig were used
to provide maximum sample recovery.
• Minimal to no water was encountered in all drill holes.
• The weight of every bulk 1 metre sample was recorded
and checked for sample recovery estimates. Sample
recovery was acceptable to industry standard.
• The sample weight of every laboratory sample was also
collected and weighed on site for future reference.
• At this early stage of exploration, it is not known if there
is a relationship between sample recovery and assay
grade.
2
Criteria JORC Code explanation Commentary
Logging • Whether core and chip samples have been geologically and geotechnically logged to a
level of detail to support appropriate Mineral Resource estimation, mining studies and
metallurgical studies.
• Whether logging is qualitative or quantitative in nature. Core (or costean, channel, etc)
photography.
• The total length and percentage of the relevant intersections logged.
• RC sample chips were collected into chip trays and are
stored for future reference.
• RC samples were logged on site during the drilling by
experienced geologists to identify key rock types and
mineralization styles.
• Sample logging was qualitative with visual estimates of
mineralization made for later comparison with assay
results.
• All one metre drill samples were logged.
Sub-sampling
techniques and
sample preparation
• If core, whether cut or sawn and whether quarter, half or all core taken.
• If non-core, whether riffled, tube sampled, rotary split, etc and whether sampled wet or
dry.
• For all sample types, the nature, quality and appropriateness of the sample preparation
technique.
• Quality control procedures adopted for all sub-sampling stages to maximise
representivity of samples.
• Measures taken to ensure that the sampling is representative of the in situ material
collected, including for instance results for field duplicate/second-half sampling.
• Whether sample sizes are appropriate to the grain size of the material being sampled.
• RC samples were collected every 1 metre into large
plastic bags and stored in rows per depth at the drill site.
• Samples were collected using a 50mm tube sampler and
composited on a two metre basis.
• Certified coarse blanks and fine standards are inserted
approximately every 35 samples and duplicates taken
every 20 samples for quality control purposes.
• The sample sizes are considered appropriate for the
geological materials sampled.
Quality of assay
data and
laboratory tests
• The nature, quality and appropriateness of the assaying and laboratory procedures used
and whether the technique is considered partial or total.
• For geophysical tools, spectrometers, handheld XRF instruments, etc, the parameters
used in determining the analysis including instrument make and model, reading times,
calibrations factors applied and their derivation, etc.
• Nature of quality control procedures adopted (eg standards, blanks, duplicates, external
laboratory checks) and whether acceptable levels of accuracy (ie lack of bias) and
precision have been established.
• Assaying of the drill samples is by standard industry
practice.
• The samples are sorted, dried, crushed then split to obtain
a representative sub-sample which is then pulverized.
• A portion of the pulverized sample is digested using a
four acid digest (Hydrofluoric, Nitric, Hydrochloric and
Perchloric) which approximates a total digest for most
elements. Some refractory minerals are not completely
dissolved.
• Inductively Coupled Plasma Mass Spectroscopy (ICP-
MS) was used to measure Ag, Al, As, Ba, Be, Bi, Ca, Cd,
Ce, Co, Cr, Cs, Cu, Fe, Ga, Ge, Hf, In, K, La, Li, Mg,
Mn, Mo, Na, Nb, Ni, P, Pb, Rb, Re, S, Sb, Sc, Se, Sn, Sr,
Ta, Te, Th, Ti Tl, U, V, W, Y, Zn, Zr,
• Au assays were provided by 30g fire assay with AA
finish.
• Every 2 metre composite sample is also submitted for
3
Criteria JORC Code explanation Commentary
Hyperspectral analysis using a TerraSpec instrument and
uploaded into the aiSIRISTM
software for mineral
identification and spectral output.
• Assays are provided by ALS del Peru in Lima which is a
certified laboratory for mineral analyses. Analytical data
is transferred to the company via email.
• Data from the laboratory’s internal quality procedures
(standards, repeats and blanks) are provided to check data
quality.
• The Company collects duplicate samples on an
approximate 1: 20 basis, and inserts coarse blanks on a
1:30 basis and fine blanks on a 1:35 basis and fine
standards are inserted on a 1:35 basis.
Verification of
sampling and
assaying
• The verification of significant intersections by either independent or alternative company
personnel.
• The use of twinned holes.
• Documentation of primary data, data entry procedures, data verification, data storage
(physical and electronic) protocols.
• Discuss any adjustment to assay data.
• No verification of intersections was undertaken. Drilling
is still wide spaced and semi-reconnaissance in nature.
• All primary sample data is recorded onto a printed sheet
on site and uploaded to a site laptop, all geological data is
recorded at the drill platform on a site laptop and
downloaded daily and onto an external backup.
• No adjustments have been made to the assay data.
Location of data
points
• Accuracy and quality of surveys used to locate drill holes (collar and down-hole
surveys), trenches, mine workings and other locations used in Mineral Resource
estimation.
• Specification of the grid system used.
• Quality and adequacy of topographic control.
• Drill hole collars including elevation are located by hand
held GPS to an accuracy of approximately 5m.
• All surface location data are in WGS 84 datum, UTM
zone 18S.
Data spacing and
distribution
• Data spacing for reporting of Exploration Results.
• Whether the data spacing and distribution is sufficient to establish the degree of
geological and grade continuity appropriate for the Mineral Resource and Ore Reserve
estimation procedure(s) and classifications applied.
• Whether sample compositing has been applied.
• RC drill-holes were sited to test for mineralization at
shallow depths within a broader intrusive complex and
testing for broad zones of stockwork veining associated
with a hydrothermal mineralised system
• Samples were composited on a 2 metre basis.
Orientation of data
in relation to
geological
structure
• Whether the orientation of sampling achieves unbiased sampling of possible structures
and the extent to which this is known, considering the deposit type.
• If the relationship between the drilling orientation and the orientation of key mineralised
structures is considered to have introduced a sampling bias, this should be assessed and
reported if material.
• Any bias due to the orientation of the drilling is unknown
at this early stage of exploration.
Sample security • The measures taken to ensure sample security. • Sample security is managed by the operator of the Project.
4
Criteria JORC Code explanation Commentary
Procedures match with Industry best practice.
• Samples are collected into securely tied bags and placed
into cable-tied plastic bags for transport to the laboratory.
Each sample batch has a sample submission sheet that
lists the sample numbers and the work required to be done
on each sample.
• Samples were transported to the laboratory by company
vehicle using trusted company personnel.
• Sample pulps (after assay) are held by the laboratory and
returned to the company after 90 days.
Audits or reviews • The results of any audits or reviews of sampling techniques and data. • No reviews or audits of the sampling techniques or data
have been carried out to date.
Section 2 Reporting of Exploration Results
(Criteria listed in the preceding section also apply to this section.)
Criteria JORC Code explanation Commentary
Mineral tenement
and land tenure
status
• Type, reference name/number, location and ownership including agreements or
material issues with third parties such as joint ventures, partnerships, overriding
royalties, native title interests, historical sites, wilderness or national park and
environmental settings.
• The security of the tenure held at the time of reporting along with any known
impediments to obtaining a licence to operate in the area.
• The Cangallo project is located approximately 25 km
east of the town of Chala in the south of Peru.
• The Cangallo project comprises 14 granted mineral
concessions. The tenements are held by Questdor which
is a 100% subsidiary of AusQuest Limited.
• There are no major heritage issues to prevent access to
the tenements. A drill permit (FTA) has been provided
by INGEMMET for the drilling program following
environmental, and community approvals.
Exploration done
by other parties
• Acknowledgment and appraisal of exploration by other parties. • No historic exploration data is available.
Geology • Deposit type, geological setting and style of mineralisation. • The Cangallo project is targeting Porphyry deposits
along the coastal belt of southern Peru. These are large
scale disseminated copper (and gold) deposits found
within orogenic belts that surround the Pacific Rim. The
deposits can be really large requiring significant drilling
to evaluate.
5
Criteria JORC Code explanation Commentary
Drill hole
Information
• A summary of all information material to the understanding of the exploration results
including a tabulation of the following information for all Material drill holes:
o easting and northing of the drill hole collar
o elevation or RL (Reduced Level – elevation above sea level in metres) of the drill
hole collar
o dip and azimuth of the hole
o down hole length and interception depth
o hole length.
• If the exclusion of this information is justified on the basis that the information is not
Material and this exclusion does not detract from the understanding of the report, the
Competent Person should clearly explain why this is the case.
• All relevant drill hole data and information are provided
below.
Data aggregation
methods
• In reporting Exploration Results, weighting averaging techniques, maximum and/or
minimum grade truncations (eg cutting of high grades) and cut-off grades are usually
Material and should be stated.
• Where aggregate intercepts incorporate short lengths of high grade results and longer
lengths of low grade results, the procedure used for such aggregation should be stated
and some typical examples of such aggregations should be shown in detail.
• The assumptions used for any reporting of metal equivalent values should be clearly
stated.
• Aggregate assay intervals quoted for the RC drill-holes
in this report are based on copper assays, using a cut-off
value of ~0.1% Cu, and maximum internal waste of 6
metres.
• For higher grade intervals (quoted as including) a 0.3%
Cu cut-off and a 6m internal waste limit were used.
Relationship
between
mineralisation
widths and
intercept lengths
• These relationships are particularly important in the reporting of Exploration Results.
• If the geometry of the mineralisation with respect to the drill hole angle is known, its
nature should be reported.
• If it is not known and only the down hole lengths are reported, there should be a clear
statement to this effect (eg ‘down hole length, true width not known’).
• All intervals reported will be down-hole lengths. True
widths will be unknown at this stage.
Diagrams • Appropriate maps and sections (with scales) and tabulations of intercepts should be
included for any significant discovery being reported These should include, but not be
limited to a plan view of drill hole collar locations and appropriate sectional views.
• All drill holes are shown on appropriate plans and
included in the ASX release.
• Relevant drill-hole cross sections will be provided when
all assays have been received and assessed..
Balanced reporting • Where comprehensive reporting of all Exploration Results is not practicable,
representative reporting of both low and high grades and/or widths should be
practiced to avoid misleading reporting of Exploration Results.
• At this early stage of drilling, only significant assay
results have been reported.
Other substantive
exploration data
• Other exploration data, if meaningful and material, should be reported including (but
not limited to): geological observations; geophysical survey result
Share your feedback
Discover